etusivu huvipuistot teemapuistot tivolit lakkautetut tietoja
Articles Linnanmäki Särkänniemi Tykkimäki Wasalandia Ålandsparken Itäkeskus Santapark Suomen Tivoli Tivoli Seiterä Tivoli Sariola Tivoli Suuronen

BUILDING UP CRAZY WORM

Updated 11.09.00

Click here to see how the Crazy Worm works

Crazy Worm

Crazy Worm is a portable roller coaster by Sartori, and purchased by Suomen Tivoli in 2000. The ride arrived in midsummer, in the middle of the season. When I took the photos, it was the 9th time the ride had been erected. Crazy Worm is a kiddie roller coaster, but this does not mean that only children can enjoy riding it. The first season has already indicated that it has been very popular with all age groups.

The technology of the ride is similar to much bigger roller coasters. The only major difference is that bigger rides have more track parts and are thus longer and higher. The erection of the ride was extremely interesting, and it was a great learning experience too. The build up was fast and smooth, since the build crew were real professionals.

Click images for larger picture

big_worm2.jpg 60k

12:00 pm. Crazy Worm load

This is the beginning of the build up. The whole ride fits inside one trailer. The worm itself peeks at the end of the trailer that acts as a station. The yellow parts are tracks, green are parts of track support structure and silver parts are used in foundation and platforms.

big_worm3.jpg 104k

Adjusting cranks

The first step is to level the trailer. This is done by adjusting the height of the legs using the cranks. The height of the station must be correct or the rest of the track will not attach to it properly. Furthermore, the front end of the station must be slightly lower in order to launch the train from the station without outside help.

big_worm4.jpg 80k

Unloading the parts

The parts are unloaded next. It's best to take one part at a time and attach them immediately, so it's necessary to dismantle the ride in proper order at the previous site. The red container is a compressor that produces the compressed air for the brakes and lap bar locking systems.

big_worm5.jpg 89k

12:30 pm. Station platform

The green bars support the platform of the station. When the ride is travelling, the platform sheets are in a vertical position. They are simply turned into their places. The fences are lifted up as soon as the floor is ready.

big_worm6.jpg 83k

Lift motor

Some heavier parts are put aside to wait for their turn, like the lift motor...

big_worm7.jpg 71k

Chain

chain, and...

big_worm8.jpg 78k

Lights

decorative lights.

big_worm9.jpg 59k

12:40 pm. Foundation

It's time to lay the foundation. This consists of 30 bars that have a specific location.

big_worm10.jpg 56k

The end of the foundation bar

At the end of the bar there is a welded part number indicating where to place it. The bars also contain adjustable legs to level the foundation.

big_worm11.jpg 58k

Assembly diagram

You can check the location of each part on this diagram. It illustrates the shape of the foundation.

big_worm12.jpg 53k

Attaching the bars

The bars slide inside the adjacent bar. A pin is pushed through both bars to secure the joint.

big_worm13.jpg 65k

13:10 pm. Tie bars

Tie bars prevent the foundation from moving. There are hooks at the end of these bars, so in theory it should be a quick operation to install them. In practice you have to adjust the position of the foundation before you are able to hook the tie bars.

big_worm14.jpg 68k

13:30 pm. Levelling the foundation

When the foundation is finished, it must be levelled properly. It can be done by screwing / unscrewing the legs while using a spirit level to check level.

big_worm15.jpg 51k

The foundation is ready

The bare foundation looks like this.

big_worm16.jpg 91k

14:00 pm. Unloading the heavy parts

When the foundation is ready, it's time to bring the lifting arm and unload the heavy parts.

big_worm17.jpg 71k

The frame

The vertical supporting pillars come next. They form the structure of the ride.

big_worm18.jpg 71k

Attaching the supports

You slide a pin through the parts and secure the joint using a cotter pin. Note that the joint is not in the centre of the green bar's end; this enables the support to lie down until you erect it.

big_worm19.jpg 66k

Electric cables

There are permanent cables inside the bars. The lights are powered simply by plugging in the mating connector.

big_worm20.jpg 69k

Building up the frame

Note the fences in the foreground. They support the pillars until the track is installed.

big_worm21.jpg 58k

14:40 pm. First section of the structure is erected

The fence will be installed to the left, between the vertical supports.

big_worm22.jpg 87k

Unloading the tracks

The tracks are lifted down and carried to their place waiting for installation. Each part weighs about 50kg. Sections of the lift hill and the trim brakes may weigh 100kg.

big_worm23.jpg 92k

16:00 pm. Installation of the track begins

The track supporting structure is erected in the same order as sections of track are installed. This step requires the participation of the whole team: One to control the lifting arm, and two men to erect the structure and direct the track to it's proper place. Usually the foundation must be slightly re-levelled in order to attach the tracks tightly.

big_worm24.jpg 51k

Installing the tracks

The fourth man sits on top of the structure and fastens the track to the frame. He uses the bar to close the gap between the sections and then secures the joint using a pin.

big_worm25.jpg 64k

Securing the joints of track

The joints of the track are secured as illustrated in the picture.

big_worm26.jpg 97k

17:30 pm. The upstairs is ready

The higher section of the track (the workmen call it "upstairs") is finished. The lower section parts can be lifted manually. At this stage the team calls it a day. The work is due to continue the following day. Note the lift hill in the left.

big_worm27.jpg 40k

09:30 am. The ends of the track

A new day begins and the work continues. Each track fragment has pegs on one end and holes on the other end. This ensures that the tracks are firmly attached. There are part numbers on the track, too. There are 49 track parts in total. The part number 1 is at the beginning of the lift hill.

big_worm28.jpg 65k

Track is almost ready

The installation of the lower section is very fast since the task does not require a lifting arm.

big_worm29.jpg 96k

10:20 am. Installing the final part

Needless to say, the last segment is always the most difficult one. The best tool in this stage is a big iron bar. However, the result is a track that sits extremely firmly on it's place.

big_worm30.jpg 104k

Vertical tie bars

The green vertical tie bars also prevent the structure from moving. This step takes lots of time, since the foundation must be lifted and adjusted until the bars meet their proper locations.

big_worm31.jpg 113k

11:20 am. The frame is ready

When all the tie bars are installed, the track looks like this.

big_worm32.jpg 99k

Cables for the lights

The worst is over when the frame is ready. Power cables are installed next.

big_worm33.jpg 88k

Installing the control panel

It's time to install the control panel and attach the electric cables and hoses for the compressed air.

big_worm34.jpg 108k

Lift hill walkway

The lift hill contains a walkway and a fence. They are needed in case there is a malfunction and the train is stranded in the middle of the lift hill. The customers can exit the ride safely if this happens.

big_worm35.jpg 112k

11:50 am. Installing the motor

It's time to install the motor on the lift hill. Note the chutes for the chain.

big_worm36.jpg 130k

12:00 pm. Chain is installed

The chain is hauled up as soon as the motor is in its proper place. Surprisingly this step takes just a few minutes.

big_worm37.jpg 60k

Lights

The decorative lights are also carried up and installed. The connectors are plugged in straight away.

big_worm38.jpg 74k

Facades

The facades are assembled. All the extra parts are stored underneath the trailer.

big_worm39.jpg 85k

The station

The other half of the station platform is installed.

big_worm40.jpg 82k

13:30 pm. Washing the train

The train is washed using a pressure washer. After washing, it's time to unfasten the train from the trailer (there are clamps at each end of the train) and send it along the track. Once the station has also been washed and the rest of the area cleaned the work is more or less done and the ride can be tested.

big_worm41.jpg 66k

Train on lift hill

The train is empty on the test run.

big_worm42.jpg 84k

14:00 pm. Return to station

Worm is returning from the test run. This is the best bend of the track. A typical ride takes three laps, one minute per lap.

big_worm43.jpg 105k

On board

This is a view from the front seat during a ride.

big_worm44.jpg 113k

A bird's eye view of the track


big_worm45.jpg 93k

Station

There is a single train consisting of 6 cars with two rows of seats per each car. There is room for one adult or two children in each row of seats.

The team of four employees spent 9 hours and 30 minutes for the build up (not including breaks). This means that the build up takes 38 manhours in total. It took twice as much when the ride was erected for the first time. Each time the ride is built up or dismantled the workers come up with some new ideas to reduce the time. It is possible to build the track using a team of three but this requires approximately 50 manhours. In theory even two men can erect it, but it takes more than twice as many total manhours as when a team of four is used. Dismantling takes only half of the time needed for assembly.

The pictures were taken in Kerava, between 6-7.9.2000. Many thanks to Petri Sariola for the technical details of the ride, and also to the magnificent build up team Ossi, Jyri, Vesku and Luki, whose work I terrorized for two days with my camera. Special thanks to Mark Cook for helping me out with the translation.

Home